Time Line

October 15, 2012
      Completed the paperwork. Money Down. Let the planning begin!

October 17, 2012
      Met with NVR Mortgage to review financing

October 25, 2012
       Met with Guardian to discuss electrical options

October 27, 2012
       Met with Stone Mark flooring to discuss granite, carpet and hard wood options

November 4, 2012
       Finalization Meeting!

November 24, 2012
       Second Deposit In!

December 21, 2012
       Pre-construction meeting!

January 2, 2013
       Break ground!

January 4, 2013
       Started Foundation

January 5, 2013
       Forms Removed

January 9, 2013
       Basic plumbing installed

January 10, 2012
       Foundation waterproofed

January 11, 2013
       Backfilled and rebar in the garage

January 15, 2013
       Garage Floor Cemented

January 17, 2013
       Lumber delivered, first floor, garage side walls completed.

February 1,2013
        Guardian Meeting #2 to confirm choices at the house

February 7, 2013
       Pre-drywall Meeting!!